AYANA LUXURY VILLAS
Construction Updates
January 2025
AYANA Villas Phuket continues to progress with precision and care. With site preparation fully completed and foundation work now 10% underway, our team remains committed to delivering world-class residences. Each step of construction reflects our dedication to quality, ensuring an exceptional living experience in every villa.
February 2025
The development of AYANA Villas Phuket continues to move forward with focus and precision. Phase 1 pile driving is now complete, and foundation work has reached 10% progress. Construction of the retaining wall has officially begun an essential feature that will shape the hillside landscape and ensure long-term stability for the estate.
March 2025
This March, AYANA Villas Phuket sees continued construction progress across all zones, with major milestones in retaining walls, foundations, and roadwork that pave the way for vertical development.
April 2025
April marked significant milestones at AYANA Luxury Villas Phuket, with structural advancements and infrastructure works progressing seamlessly. Discover how our vision of luxury living is taking shape.