April 2026

CONSTRUCTION UPDATE

Strong momentum continues across AYANA Soluna Villas, with Villa 7 fully complete and Villa 43 progressing through final corrections ahead of completion.

Villas 15, 16, 17 and 19 are advancing well through plastering, floor levelling, and pool construction, while Villa 36 has reached the exciting milestone of swimming pool tiling.

Villa 32 continues ceiling frame and electrical wiring installation, and Villa 42 is progressing through external wall plastering and MEP work. The main gate has reached 97.21% completion, with landscaping now actively underway.