May 2026
CONSTRUCTION UPDATE
Exciting progress continues across AYANA Soluna Villas this May, with Villa 7 remaining fully complete and Villa 43 continuing through final corrections ahead of handover.
Villas 36, 38 and 40 are advancing into the highly anticipated pool tiling stage. Villa 32 progresses with ceiling frame and electrical work at 60% overall completion.
Villas 23 and 24 continue prefabricated wall installation, and the main gate entrance gates installation is now underway, bringing the community's arrival experience closer to completion.