July 2025
The construction of AYANA Heights Seaview Residences is progressing steadily across multiple buildings.
• Building E has advanced significantly with pile cutting work ongoing and retaining wall construction at 90% completion.
• Building F shows solid progress with new bored pile work underway and footing excavation in progress.
• Building G is preparing for new needle drilling work, while Building H has achieved 50% completion on bored pile operations.
• Building C has completed piling work with dynamic testing on 800mm diameter piles, and the retaining wall construction has reached 100% completion for both footing and wall concrete pouring, with backfill soil work now underway.
Overall, the project maintains strong momentum with steady progress across all structural and foundational elements throughout the development.