August 2025

The construction of AYANA HEIGHTS SEAVIEW RESIDENCES shows excellent progress across all buildings.

Building E has completed 100% of piling work with retaining wall construction at 90% and pile cutting work advancing at 20%.

Building F has achieved full completion of piling, excavation footing, and pile cutting work.

Building G has finished piling work entirely with pile cutting progressing at 30%.

Building H demonstrates outstanding progress with 100% completion of both piling and pile cutting work. .

Building C has prepared the construction area and commenced piling operations.

The retaining wall construction maintains 100% completion for both footing and wall concrete pouring with backfill work ongoing. Overall, the project is demonstrating significant advancement across all phases.