September 2025

Building B has commenced pile driving operations at 3% progress with dynamic pile testing underway. Building C has completed pile driving and is proceeding with pile cutting at 10% completion. Building D is advancing with soil excavation and dynamic pile testing. Buildings E and G continue pile cutting work at 10% progress.

Building F has reached 10% completion, proceeding with raft foundation construction and rock drilling. Building H demonstrates the highest progress at 12%, advancing with raft foundation construction. Road Zone 1 retaining wall work is completed at 10%, while Road Zones 2-4 progress with pile driving and soil cutting operations.