February 2026
CONSTRUCTION UPDATE
Buildings G and H are leading progress, both reaching 97% structural completion with teams now focused on stair construction, MEP work, and Cera wall installation.
Building E has advanced to the 3rd floor (32% structural), while Building B is progressing with its first-floor slab and water tank construction.
Foundation work is nearing total completion across the site, with Building A reaching 89% as it transitions into column and beam construction for the water tank.