January 2026
CONSTRUCTION UPDATE
Development at AYANA Heights remains on schedule with significant milestones achieved this January. Foundation work for Buildings B, C, E, F, G, and H is now 100% complete, while Building A has reached 75%. Vertical progress is most visible at Building H, which has reached 95% structural completion, followed by
Building G at 85%, with teams now proceeding to the roof floor.
Building E structural work is at 10% and Building F at 2% as we transition into floor and slab construction.
Building B is currently focused on basement floor flat slab work and retaining walls, while Buildings A, C, and D proceed with column, beam, and footing construction.