CONSTRUCTION UPDATE

AYANA Heights continues to rise impressively, with Buildings G and H leading the way at 98% structural completion, now advancing into Cera wall cladding and MEP installation.

Building E has reached the 5th floor construction phase, while Building F progresses steadily through its 2nd floor.

Buildings B and C are advancing with column and structural work well underway, as foundations for Buildings A and D continue to progress confidently on schedule.