CONSTRUCTION UPDATE

AYANA Heights continues its impressive upward trajectory this May, with Building E reaching a landmark moment as construction advances to the roof floor - a significant visual milestone for the development.

Buildings G and H are progressing strongly through Cera wall installation and MEP work, while Building F advances through its 4th-floor columns.

Building C is now rising through its 3rd floor structure, with pool construction also underway, and foundations for Buildings A and D continue steadily on schedule.