June 2026
Construction Update
AYANA Heights Seaview Residences is advancing very well this month.
Building H leads the way, now moving into architectural and interior installation work, while Buildings E and G have completed their structural frames and progressed to Cera wall and MEP fit-out.
Building F continues rising with column work on its 6th floor, and Building C is taking shape with pool construction and column work underway on the 5th floor.
Buildings A and D remain in advanced foundation stages.
Across the site, road and retaining wall works continue to strengthen our community's foundations for the sea view lifestyle ahead